Capacity payment

Capacity payment is a tariff model in which payment is linked to installed or agreed power capacity (kW/MW) rather than the amount of energy (kWh/MWh) consumed or produced. The model has been introduced to make payments for the electricity grid more cost-reflective, because a large part of the grid costs are driven by the need for capacity at times when the grid is under the greatest strain. For businesses and public sector players, capacity payment can change the economics of electricity consumption, own production, and new connections, because the "peak" in your power draw or feed-in becomes more important financially. For private individuals with solar cells, the topic is particularly relevant in conjunction with changed billing and tariff conditions, where the timing of production and consumption becomes more crucial.

What does capacity payment (power payment) mean in practice?

Definition: Capacity payment is a tariff payment based on the agreed or installed capacity (kW/MW) rather than energy consumption (MWh). The key factor is the maximum power that a plant is entitled to draw from or feed into the grid at any given time. In practice, therefore, it is not just a question of "how much" you use over a year, but "how quickly" you can draw or supply power at the most demanding times.

In a project, this means that the economics depend not only on how many kWh/MWh you use or produce, but also on the power level (kW/MW) that is dimensioned and agreed upon in connection with the connection. It is typically in the dimensioning that the big decisions are made: How high a simultaneity do you expect in operation? How much buffer do you want for expansions? And what consequences does this have for the fixed costs?

The capacity payment is used to cover grid-related costs in transmission and distribution grids, e.g., transformers, stations, and cables. These assets must be able to handle peak loads, which is why power is a relevant "measure" of the capacity that the grid must make available to you.

Calculation: The payment can typically be expressed as a tariff coefficient for area/voltage level multiplied by the agreed capacity (MW or MVA). In your finances, the capacity level thus becomes a concrete parameter in line with the investment budget, operating profile, and any expansion plans. A practical way to work with this is to separate "must have" (necessary capacity for operational reliability) from "nice to have" (capacity for rare peaks), so that the choice becomes more manageable.

Why has capacity payment become part of the tariff model?

Cost authenticity: Capacity payment is based on the principle that a customer group should pay for the costs it incurs through its use of and access to the grid. Grid infrastructure is largely dimensioned according to maximum power (capacity) rather than total energy consumption. When dimensioning is determined in practice by peak loads, it makes sense that part of the payment also follows this logic.

Changed cost structure: As the green transition progresses, costs are shifting from fuel to investments in infrastructure. This makes pure energy tariffs (payment per kWh) less suitable for covering grid costs. For you, this means that tariffs can be perceived as more of a "fixed" expense that does not decrease proportionally, even if energy consumption is optimized.

Capacity constraints: Increased wind and solar power generation increases the need for grid reinforcements, which are mainly driven by capacity requirements. This is particularly relevant when many plants are generating power or many consumers are drawing power at the same time, as this places demands on cables, transformers, and substations.

Flexibility: The model can provide incentives to reduce maximum power consumption or plan consumption/production so that the grid is less burdened during peak periods. In practice, this could mean, for example, that more planned operation, load management, or conscious dimensioning could be an alternative to "buying" more grid capacity. In some cases, this could be cheaper for society than expanding the grid, and for you, it could make operating costs more predictable.

Capacity payment: who is covered, and when did it come into effect?

Capacity payments for electricity producers will apply from January 1, 2023.

From January 1, 2023, producer payments were formally implemented for new electricity production facilities (with temporary operating permits issued after this date). In practice, producers pay both a one-time connection fee and ongoing tariffs for feed-in. For you as a project developer or plant owner, this means that grid connection is not only a technical milestone, but also a financial decision, where the choice of connection level and agreed capacity can have a direct impact on the overall economics of the project.

Capacity payments for large electricity consumers will apply from January 1, 2025.

From January 1, 2025, capacity payments will be introduced for larger consumption facilities connected to the transmission grid (above 100 kV). Here, consumers pay both a power subscription (fixed annual payment per MW) and an energy tariff (øre/kWh). This shifts the focus of the tariff: even if annual energy consumption is stable, changes in peak load can have a greater impact on the budget, making it more relevant to know your load profile and the times when you peak.

Power plays a greater role in the 10–60 kV distribution network

In the distribution network (10–60 kV), part of the costs are charged via power payment and the rest via energy tariff. At the same time, the previous "availability tariff" for larger customers at 10–60 kV will be abolished from New Year 2025 and replaced by increased power payment. In practice, this means that it will become even more important to understand how much power you actually need and how it varies during operation, because the fixed part of the tariff will follow the power level to a greater extent.

How capacity payment works for consumption with power subscription and energy tariff

Two parts: For larger consumers, payment is typically divided into two components, which together reflect both capacity and ongoing energy flow. This gives you two "levers" to work with: managing peak load (power) and reducing losses/energy (kWh).

  • Power subscription: Fixed payment per MW/year (capacity) for the reserved/available power.
  • Energy tariff: Variable payment per kWh, which covers costs such as grid losses.

Calculation of power: The power payment can be charged based on a calculated maximum draw based on measured consumption from the collective grid over the past 12 months. For direct customers of Energinet, it is typically calculated based on the agreed draw right in the connection agreement. You should therefore actively consider which "reference" will be decisive: historical measurements or an agreed right, which in practice becomes the financial ceiling?

Consequence: If your capacity is dimensioned high "just to be on the safe side," this can result in higher fixed costs year after year. Conversely, under-dimensioning can later trigger expensive and complex expansions, because grid connection often involves both technical and administrative processes. This makes early clarification of capacity requirements a key decision point.

A practical approach is to describe your operations in a few specific scenarios: normal operations, peak operations, and future operations (e.g., expansion). When the scenarios are clear, it becomes easier to assess whether the peak can be handled through planning (e.g., shifting loads) or whether it must be covered by grid capacity.

Capacity payment for producers with connection fees and feed-in tariffs

Connection fee: New production facilities pay a standard connection fee (one-time payment) per MVA. The level depends on factors such as connection level, geographical location (geozones), and facility type. The connection fee is therefore a key factor in your business case and your choice of technical solution, because the voltage level and capacity choice affect the total investment budget.

Price ranges (standard contributions): For 2025–2026, there are large variations depending on level and zone, e.g.:

  • High voltage (30–60 kV): approx. DKK 50,000–69,000/MVA depending on geozone.
  • Medium voltage (10–20 kV): approx. 154,000–1,773,000 DKK/MVA.
  • Low voltage (0.4 kV): approx. 168,000–235,000 DKK/MVA.

This difference shows why it is important to clarify the connection level and terms early on. If you change the design or capacity size late in the process, it can affect both the one-time payment and the subsequent pricing, and it can create uncertainty in the budget and schedule.

Feed-in tariff: Producers also pay ongoing feed-in tariffs (typically øre/kWh). Geographical differentiation was removed from June 2025, so producers pay the same tariff regardless of location (specified as approx. 0.3–0.9 øre/kWh depending on the area). This makes the ongoing tariff more uniform across geography, but it does not change the fact that connection fees and capacity choices may still vary depending on connection conditions and zone principles.

Geozones: Geozones are used to divide the country according to grid load: red (production surplus), yellow (balanced), and green (consumption-dominated). The map is updated based on actual flows between distribution and transmission grids. For you, the point is not just the color on a map, but that the zone logic can be a condition that must be handled as a project risk: What assumptions underlie your connection economics, and how robust are they if framework conditions or load patterns change?

Capacity payments and self-generation: what does this mean for prosumers?

For self-producers with consumption (e.g., companies with solar cells and operations), the tariff landscape is affected by several changes. In practice, this means that the value of self-production depends to a greater extent on how production can be used locally and how connection conditions and tariffs interact with your load profile.

  • Net metering phased out: From January 1, 2024, the previous net metering (instant metering, group 2) was gradually phased out. Private solar cell owners can now only use group 3 (instant metering), where electricity must be used at the same time as it is produced or sold to the grid.
  • Co-location: Legislative changes in 2023 made it possible to co-locate consumption and production, which provides special tariff options for self-producers.
  • Local associations: Several customers can share consumption and production under special conditions when they are connected to the same transformer station.

When capacity payments become more significant, it is also important to understand how your connection terms and power requirements are determined, because changes to the project design can have tariff implications. This is especially true if you change components or operations that affect peak loads, e.g., by increasing the size of the inverter or changing when loads are settled. A good next step is therefore to get a clear picture of which "peaks" come from production and which come from consumption, so you can assess whether they can be smoothed out in practice.

Risks associated with capacity payments and how to manage them in practice

Capacity payments make dimensioning and operation more sensitive to peak loads. Therefore, you should treat tariff conditions as a project track in line with technology and authorities, so that the economy is not surprised late in the process. The typical pitfalls can often be handled with early clarifications and a clear decision-making logic:

  • Underestimated capacity requirements: Under-dimensioning can lead to subsequent expansions that are both expensive and complicated.
  • Oversizing: Excessive capacity can result in unnecessarily high capacity payments year after year.
  • Project changes: Changes in, for example, inverter size, battery connection, or production/consumption profile may affect both one-time payments and ongoing tariffs.
  • Geographical risk: Geozones may change over time, which may affect standard contributions in future periods.
  • Budget uncertainty: Tariffs may be adjusted, partly because under- and over-coverage may be included in budgeted coefficients.

At XOLTA, we typically work to translate these risks into specific decision points in the project plan: clarification of power requirements, choice of connection level, and an operating strategy that matches your actual load and future development. This often involves answering three very practical questions: What is your expected maximum? How often do you reach it? And what happens financially if you scale up or down slightly? Once these questions have been clarified, it becomes easier to choose a solution that is robust in operation.

Alternatives and supplements to capacity payment in the tariff

Capacity payment is one way of setting tariffs, but it is part of a broader tariff and market landscape. In practice, you will often encounter a combination of several mechanisms that affect your total network costs. It is therefore useful to be able to distinguish between what affects the fixed part (capacity) and what affects the variable part (energy and time placement):

  • Volumetric tariffs: Payment per kWh (simple, but less cost-effective compared to capacity-driven networks).
  • Time-differentiated tariffs: Variation according to time of day/season to reflect load.
  • Geographical differentiation: Tariffs depend on location (geozones), even without actual capacity payments.
  • Local flexibility markets: Concepts where flexibility can be traded locally as a supplement to tariff incentives.
  • Direct lines: Private connections bypassing the public network for specific customer categories.
  • TSO-DSO tariffing: A model under development, where tariffs are charged to a greater extent between system operators and distribution companies, expected around 2027.

As a decision-making aid, it may be worth bearing in mind that the different models typically reward different behaviors: Volume tariffs reward low consumption, time differentiation rewards shifting consumption to other times of day, and capacity payments reward lower peak consumption. Once you know what "signal" the tariff sends, it becomes easier to choose the measures that suit your operations and investment horizon.

FAQ about capacity payments

  • What does capacity payment mean? It is a tariff model where payment is based on installed or agreed power capacity (kW/MW) rather than energy volume (kWh/MWh).
  • When was capacity payment introduced in Denmark? Producer payment was implemented from January 1, 2023, for new electricity production facilities, and from January 1, 2025, capacity payment has been introduced for larger consumption facilities connected to the transmission grid.
  • What is the difference between a power subscription and an energy tariff? A power subscription is a fixed payment per MW/year for the reserved capacity, while the energy tariff is a variable payment per kWh, partly to cover grid losses.
  • How is the basis for the power payment calculated? It can be calculated based on the estimated maximum draw based on measured consumption from the collective grid over the past 12 months, or as agreed draw rights in the connection agreement for direct customers.
  • What one-time payments can producers face when connecting to the grid? New production facilities pay a standard connection fee per MVA, which depends on the voltage level, geozone, and facility type, and can vary significantly.
  • What specific changes apply to prosumers? Net metering (instant metering, group 2) will be phased out gradually from January 1, 2024, and co-location and local associations will be permitted under specific conditions.

Contact us

Do you have questions or need advice? Our experts are ready to help you.

Contact support

If you would like to contact support, please call +45 35 153 123 or send an email to support@xolta.com.

Contact sales