Network connection

Grid connection is the process whereby a new electrical installation – as a consumer, producer, or both – is connected to the collective electricity supply grid in Denmark. For many, it is a matter of getting electricity to a home or business, while others need to connect solar cells, wind turbines, or a battery system so that production and flexibility can be utilized in practice. Rules, timelines, and finances depend primarily on the size of the system, voltage level, and local grid capacity. Here you will find a comprehensive overview of concepts, processes, requirements, and typical pitfalls, so that grid connection can be planned with realistic expectations for both time and costs.

What does grid connection mean in practice?

Grid connection is the connection of an electrical installation to the collective electricity supply grid. The collective grid comprises both the transmission grid (operated by Energinet at voltage levels above 100 kV) and the distribution grid (operated by local grid companies at 0.4 to 60 kV).

In practice, grid connection is not just a matter of "putting a cable in the ground," but of agreeing where the connection will be made, what framework applies to operation (off-take and/or feed-in), and what documentation must be in place before the installation can be energized and put into operation. Clarifying these conditions early on often prevents delays later on.

Connection point: The physical boundary between the grid operator's grid and your internal installation (collection grid). For private households, this is typically located at the meter box. For larger installations, the connection point may be a transformer station or a high-voltage connection. The connection point is important in terms of responsibility, costs and, in practical terms, who is to carry out which parts of the work.

Network connection and network access: Full or limited network access

A key decision when connecting to the grid – especially for production facilities – is whether to connect with full or limited grid access. This decision affects both finances and operational risk, and should be made based on how critical it is for the facility to be able to supply without interruptions or downregulation.

  • Full grid access (FNA): Unlimited right to have the amount of electricity required by the installation transported. The customer pays the standard connection fee and cannot be disconnected or down-regulated due to grid capacity issues.
  • Limited grid access (BNA): The customer agrees to be disconnected or down-regulated in the event of grid congestion – typically without prior notice. In return, a reduced connection fee is paid.

BNA has been introduced to enable new projects to be connected more quickly when the alternative is to wait for grid expansion. However, it is a real operational risk that must be assessed against financial and business-critical needs. As a rule of thumb, you should clarify what a downward adjustment means for you: Is it a manageable limitation, or does it affect deliveries, operational reliability, or finances to such an extent that FNA is necessary? If you choose BNA, your operational setup and internal expectations should be designed to accommodate variations in capacity.

Scope of supply and scope of delivery for grid connection

When connecting to the grid, the framework for how much you can purchase and/or feed into the grid is established. It is crucial to agree on these values early on, as they affect the dimensioning of internal installations and the technical requirements that must be documented.

  • Scope of supply: How much a consumer may purchase (typically specified in amperes or MVA depending on the level).
  • Feed-in volume: How much a producer is allowed to feed into the grid.

For small private installations, the standard supply and connection capacity is often 25 A, while businesses and industry may have significantly larger capacities. In practice, the scope is the "capacity limit" for your connection: if your needs change later, it may require a new application, an adjusted agreement, and in some cases, remodeling or expansion. Therefore, it makes sense to identify both current needs and realistic scenarios before submitting the application.

Rules for grid connection and central authorities

Grid connection is regulated by the Electricity Supply Act and the Grid Connection Order (BEK No. 547 of 29/05/2024). Among other things, the Order stipulates that the grid and transmission company must designate a connection point and a voltage level that will result in the lowest total costs for grid connection.

In practice, this means that the connection solution is not only assessed on the basis of what is most convenient for the project, but also on the basis of the overall system economy. This can have an impact on where the connection is located and what voltage level is chosen, especially for larger installations or in areas with limited capacity.

Technical requirements for grid connection of production also comply with EU Regulation RfG (Commission Regulation (EU) 2016/631), which harmonizes requirements across the EU. In Denmark, the requirements have been implemented via the Electricity Supply Act and technical conditions drawn up by Energinet and the grid companies. For you, this means that both design and documentation must be planned so that they match the technical conditions from the outset – otherwise you may risk additional rounds of adjustments close to commissioning.

The Danish Energy Regulatory Authority: Approves methods used by network companies to set tariffs, standard fees, and connection charges. Only approved methods may be used. If anything in an offer or calculation seems unclear, it is therefore important to clarify which method has been used.

Process for connecting small installations (private and small businesses) to the grid

For small consumer installations (typically under 125 kW for businesses and private homes), grid connection is relatively standardized. This makes the process more predictable, but it is still advantageous to clarify the scope of delivery, the location of metering, and any practical issues on the property so that the installation can be carried out without redesign.

  1. Request: Send to the local network company with your address and desired delivery scope (often 25 A). Ensure that your address details and contact person are correct so that the case is not held up due to formalities.
  2. Response time: The network company typically responds within 1-2 weeks. The response forms the basis for further planning, including whether changes to the connection are necessary.
  3. Connection fee: Paid in cash prior to installation. It is worth clarifying the payment flow and timing early on so that it does not become a practical obstacle to the schedule.
  4. Installation and notification: An electrician installs the internal part and notifies the installation via the network company's ISB system (installation form). It is typically at this stage that requirements for meter placement, fuses, and internal cabling are specified.
  5. Physical connection: If no expansion is required, it often takes 4-8 weeks from approval to physical connection. Please plan the work so that internal installations are ready in good time when the network company can perform the connection.

A practical way to reduce the risk of delays is to ensure that the electrician has all the relevant information from the network operator before work begins, and that the notification in ISB matches the solution that is actually installed at the address.

Process for connecting production facilities to the grid (125 kW to 3 MW)

For solar power plants and other production facilities in the range of 125 kW to 3 MW, grid connection is more complex and is typically carried out in five phases. Here, it is particularly important to keep track of the connection between technical design, application material, and subsequent testing and documentation, because changes late in the process can trigger additional case processing.

  1. Clarification and preliminary investigation: The project is specified in detail, and possible connection points are assessed. Clarify at an early stage whether the connection point and voltage level are expected to suit your planned scope of connection, so that the project is not dimensioned in a way that will require changes later on.
  2. Application and grid connection agreement: Technical application submitted. The grid company issues a grid connection agreement with requirements, scope of connection, and connection fee. Processing time can be 2-6 weeks. Review the agreement thoroughly to ensure that the conditions, framework, and requirements are understood before installation begins.
  3. Establishment: The network company establishes cables, transformers, etc. If network expansion is required, the schedule can take months or even years. In this phase, coordination between your contractors and the network company's work is often crucial to meeting milestones.
  4. Connection and energization: Energization is permitted when the infrastructure is ready and the installation has been reported via ISB. Ensure that the "as built" and the report are consistent so that there is no doubt about what is actually being connected to the grid.
  5. Testing and commissioning: Technical tests are carried out. First, a temporary grid connection permit (ION) is issued, followed by a final grid connection permit (FON). Plan the test process so that relevant documentation can be provided without delay between ION and FON.

As project managers, you should have a clear plan for who delivers which documents when, and who handles the dialogue with the network company. This is often the most effective way to avoid unnecessary iterations at the end of the process.

Grid connection of large-scale installations: Timetable, environmental requirements, and grid expansion

For larger production facilities (over 3 MW), grid connection is often complex and influenced by both regulatory processes and the need for grid reinforcements. Here, grid connection should be viewed as a separate track in the project with its own dependencies, because both grid expansion and approvals can set the critical timeline.

  • Permits above 25 MW: Requires an establishment permit and an electricity production permit. Case processing typically takes 6-10 weeks after full disclosure. This emphasizes how important it is to submit complete documentation so that the case is not halted due to missing information.
  • Environmental assessment: Larger projects may require environmental assessment (EIA) and consideration of, for example, Natura 2000, which can significantly delay projects. Case processing times have been increasing since 2023-2024. This makes it relevant to clarify environmental tracks and network tracks in parallel so that one does not inadvertently delay the other.
  • Delays in grid projects: A report from Q2 2025 shows that 71% of Energinet's transmission projects have been postponed compared to the original schedules. This should be included in your risk assessment and milestone plan when the project depends on reinforcements in the transmission grid.

For large projects, the time from application to commissioning can in practice end up being several years, especially if network expansion and extensive regulatory processing are required. A robust plan therefore typically contains clear decision points where you can continuously assess whether the project's assumptions still hold true before committing to the next phase.

Economics of grid connection: Connection fees and grid tariffs

Grid connection fee: A one-time fee for establishing/expanding the connection and local infrastructure. The fee must be paid in cash in advance. For many projects, it is advantageous to treat the fee as a concrete milestone in the budget and schedule so that the establishment is not delayed by internal approvals or payment processes.

  • Private homes (2026 prices, excluding VAT): Detached house 25 A approx. 16,400-17,950 kr. Terraced house 25 A approx. 13,150-14,360 kr. Standard apartments (16 A) approx. 8,950-10,050 kr.
  • Business: Typically structured per ampere or per MVA depending on voltage level (e.g., approx. DKK 1,200-1,450/A for small businesses; approx. DKK 600,000-700,000/MVA for larger businesses).
  • BNA for production: Often 50-70% lower connection fees than full grid access when the scheme can be applied.

Regardless of size, you should read the calculations and terms and conditions as part of the project's assumptions: What scope of delivery and installation has been calculated, and what specifically does the contribution cover? This is typically where misunderstandings can arise if the project is changed along the way.

Network tariffs: Ongoing payment for electricity transmission, charged via the electricity supplier. Typically a fixed subscription plus a variable tariff per kWh – and for larger companies there may be a power tariff based on maximum power. This means that your operations and load profile can affect your ongoing costs, so it is important to include tariffs in your overall assessment of the solution's economics.

Technical requirements and documentation for grid connection

All grid-connected installations must comply with technical conditions that follow Danish regulations and EU RfG requirements. The technical requirements must not only be met in theory, but also be documented in a way that the grid company can approve. Therefore, the documentation work should be planned as part of the project – not as a final formality.

  • Voltage tolerance: The system must be able to tolerate ±10% of the nominal voltage under normal operating conditions.
  • Frequency tolerance: Typically 49.5 Hz to 50.5 Hz during normal operation.
  • Power quality: Installations must not cause unacceptable disturbances, such as harmonics or rapid voltage changes (flicker).
  • Fault protection: Production facilities must have functional fault protection and shut down quickly in the event of a grid fault (typically around 200 ms).
  • Documentation: Declarations of conformity and often testing under ION before FON can be issued.

Lack of documentation may mean that final grid connection approval (FON) will not be issued. To avoid documentation becoming the decisive bottleneck at the end, it is advantageous to clarify early on which declarations and tests are expected and who will provide them (supplier, electrical installer, or consultant). This ensures a more controlled process from ION to FON.

FAQ about grid connection

  • What is grid connection? Grid connection is the connection of an electrical installation to the collective electricity supply network.
  • How long does it take to connect to the grid? For simple connections without grid expansion, it often takes 4-8 weeks from approval to physical connection, while larger projects involving grid expansion and regulatory processes can take several years.
  • What is the difference between full and limited grid access? Full grid access provides unlimited transmission rights and no capacity-related curtailment. Limited grid access involves a risk of interruption/curtailment in the event of congestion, but with a reduced connection fee.
  • How much does it cost to connect a private home to the grid? The standard connection fee for detached houses (25 A) in 2026 is around DKK 16,400-17,950 excluding VAT, with variations depending on local conditions.
  • What technical requirements apply to grid connection of production? Requirements include voltage and frequency tolerances, power quality, fault protection, and documentation, often via declarations of conformity and testing prior to final approval (FON).
  • When can limited grid access (BNA) be used? BNA can be used if the facility is connected at a minimum of 10 kV, does not require grid expansion, can be made interruptible, and there is available capacity in the grid.

Contact us

Do you have questions or need advice? Our experts are ready to help you.

Contact support

If you would like to contact support, please call +45 35 153 123 or send an email to support@xolta.com.

Contact sales