Island operation

Island operation means that a building, area, or installation can be powered locally without relying on the collective electricity supply grid. It is typically used as a controlled emergency power function when the grid connection is lost or when it is deliberately disconnected. In Denmark, the electricity supply is very stable, but interest in island operation has increased in line with the increased focus on preparedness and operational reliability. Here you will find an overview of what island operation is, what is required, and how to approach it correctly in practice.

What island farming is and what it is not

Island operation (islanding) is an operating concept in which electricity consumers are supplied locally by their own energy sources when the connection to the main grid is interrupted – either due to a fault or as a planned disconnection. In practice, island operation can apply to everything from a detached house to a factory, a hospital complex, or critical infrastructure.

The key point in island operation is that electricity cannot be imported from outside. Therefore, there must be a balance between production, storage, and consumption, and there must be clear priorities for which loads are to be kept running. In practice, this means that you need to know what must be turned on (critical functions), what may be turned on (important functions), and what does not need to be turned on when you are running on local supply.

Planned and unplanned drift

A distinction is typically made between two situations that require very different approaches in terms of both design and operation:

  • Planned island operation: A controlled solution established in advance so that the plant can continue to operate for a defined period under known conditions.
  • Unintended island operation: When a production facility continues to supply a grid segment after separation from the main grid without control. This can create serious safety and stability problems.

As a decision-maker, it is worth noting that planned island operation is about ensuring continuity for selected loads, while unplanned island operation is a fault condition that must be prevented and handled with proper protection and disconnection.

Island operation as preparedness: Why the topic is becoming more important

Interest in island operation is largely linked to the desire to maintain operations during power outages. This applies both to private individuals who want power for critical functions in their homes and to businesses/public sector organizations, where even short outages can have major consequences for operations, safety, and service.

At the same time, Denmark's electricity supply is among the most stable in the world, with a security of supply of 99.99 percent. Therefore, in many cases, island operation is most relevant as a security and contingency measure – not as a daily operating strategy. However, this does not change the fact that island operation can be a practical way to reduce vulnerability if you have clarified three basic questions in advance: What needs to be kept running, for how long, and how do you ensure a stable and secure transition when the grid fails?

Island operation with solar cells and battery in a typical solution

Islands are often supplied by a combination of local energy sources such as batteries, generators, and possibly solar cells or wind turbines. For private individuals, a typical solution is a solar cell system combined with battery storage and automatic switching, so that selected circuits continue to operate during power outages.

It is important to be specific about what "continues" means in practice: Many choose to establish a separate, prioritized electrical circuit for selected consumers. This way, you avoid non-critical loads draining the battery, and you get more predictable operating time during emergency operation.

What should be able to run during island operation?

Before dimensioning, the need must be clarified: Which functions are critical, and which can be disconnected? A practical way to start is to review your installations and mark the functions that are important for safety, health, operation, or communication. Examples of critical loads can be:

  • Private: Refrigerator/freezer, heating, lighting, and communications (internet/telephone).
  • Agriculture: Pumps for animal watering, ventilation, and environmental control in livestock buildings.
  • Businesses: Critical IT systems, lighting, and processes that must not be interrupted.

Once the list has been made, the next step is to assess which of these loads can be simultaneous and which can run alternately. This affects both the choice of inverter and the actual operating time of the battery during island operation.

Technical requirements for island operation: Disconnection, detection, and safety

Island operation is regulated by technical requirements at Danish and European level. A key framework is RfG (Requirements for Generators), which has been implemented in Danish technical requirements for electricity generation plants. The purpose is to ensure that generation plants do not pose a risk to the overall electricity grid and that plants handle unintended island operation correctly.

From an operational and project perspective, this means that island operation is not just a matter of "having a battery," but of documented safe disconnection and proper protection. It should therefore be included as a fixed requirement in the requirements specification and test plan if you purchase or retrofit a solution.

Detection of unintended drift

Production facilities must be able to detect unintended islanding and disconnect from the collective grid if it occurs. In Denmark, only passive detection methods (measurement of grid parameters such as frequency and voltage) are used. It is not permitted to use vector jump relays (ANSI 78) or active islanding detection to protect facilities connected to the collective grid.

The key principle is that power from a solar cell and battery system must not be fed into the public grid during a power outage. Off-grid operation must be limited to the specific property and must not inadvertently supply neighbors or an area outside the property. This is also why you cannot "share" your off-grid operation with other buildings via the public grid: the limitation is part of the safety measures, not an optional feature.

Hybrid Inverters and Transfer Switching Equipment (TSE)

If solar cells are to be supported by batteries, a hybrid inverter is required. If off-grid operation is desired, an investment must be made in a control box (Transfer Switching Equipment, TSE), which ensures safe disconnection from the collective grid and controlled switching to off-grid operation.

In practice, TSE and the associated switching logic are what make the transition manageable: they ensure that no undesirable "feedback situations" arise and that the system switches in such a way that priority loads can be supplied within the limits for which the system is designed. This is also where the demarcation to selected circuits is typically established, so that island operation does not have to "carry" the entire installation.

Island operation in practice: Dimensioning, switching, and stable operation

An island operation solution will only work in practice if it is planned, dimensioned, and tested according to your actual needs. This is especially true when several considerations need to be balanced: desired operating time, how many loads need to be active, and how robust the transition needs to be.

A general piece of advice is to think of island operation as an emergency function that must be able to be operated and controlled, even when things get busy. This requires a clear plan for what happens in the event of an outage, who does what, and how you verify that the system actually delivers the expected function.

Step-by-step process from need to operational solution

A practical process helps you avoid classic mistakes in requirements, dimensioning, and operation. The following steps are often used as a simple but effective framework:

  • Needs assessment: Identify critical functions and desired duration during outages.
  • Prioritizing loads: Decide which loads should be able to run simultaneously and which can be disconnected.
  • Switching selection: Manual switching, automatic switching (UPS function), or hybrid with generator.
  • Dimensioning: The battery, inverter, and any solar cells are dimensioned according to the priority load.

Once you have completed these steps, it will be much easier to translate your wishes into specific requirements: Which circuits need to be backed up, which starting currents need to be handled, and what type of switching makes sense in daily operations.

As a rule of thumb, it is often said that the battery should be dimensioned to be able to supply critical loads without solar production for at least 8-12 hours, depending on weather uncertainty. In practice, you should use the rule of thumb as a starting point and then validate it against your own load profile and the situations you actually want to be covered for.

Installation and electrical safety

Installation must be carried out by authorized electricians and comply with Danish electrical installation standards. A physical separation must be established between the collective grid and the local island operation system, typically via a transfer switch/TSE or inverter function that disconnects correctly. The Danish Safety Technology Authority's guidelines also emphasize that installation must take into account special areas (e.g., damp environments) and include requirements for protection against indirect contact and a correct residual current device (type A or B).

To make it operational, it is a good idea to agree on how island operation will be tested: What will be disconnected, which loads will be verified, and how will it be documented that switching and disconnection are occurring as expected? Regular testing is not just "nice to have"; it is often what determines whether the emergency response function actually works when you are faced with a real outage.

Economics of island operation: Price level, payback, and replacements

The cost depends on the size of the system and the technology chosen. A complete solar cell system with battery and inverter for an average household of four people typically costs around DKK 130,000. For existing solar cell owners, retrofitting a small battery starts at around DKK 35,000, and a standard inverter typically costs between DKK 10,000 and DKK 25,000, depending on the battery size.

An example for a detached house with an annual electricity consumption of 4,000 kWh and a roof area of 50 m² shows a total cost of around DKK 120,000, with potential annual savings of around DKK 8,000 and a payback period of approximately 15 years.

In another example, the annual net cost of electricity is reduced from approximately DKK 5,742 without a battery to approximately DKK 2,097 with a battery. The battery provides an additional saving of approximately DKK 3,645 per year, but the investment in the battery is significant, and the payback period is typically stated as being between 10 and 15 years.

When assessing the economics, it is important to distinguish between two considerations: pure energy savings in everyday life and the value of increased security of supply. Emergency operation is often chosen precisely because outages can be expensive or critical, even though the payback period for the energy component may be long. This makes it relevant to define what emergency operation "must cost" in terms of preparedness and what is expected of the function during an outage.

It is important to factor in replacements: Lithium-ion batteries typically have a lifespan of around 10–15 years, and replacement can cost DKK 30,000–50,000. The inverter may also need to be replaced after 10–15 years. To avoid unpleasant surprises, you should therefore draw up a simple plan for servicing, monitoring, and expected replacements so that the total cost can be realistically assessed from the outset.

Risks and pitfalls of island farming that you should avoid

Island operation can provide greater robustness, but only if the solution has been thoroughly thought through in terms of both technology and operation. Here are the typical conditions that cause problems, as well as what they mean for you in practice:

  • Unintended drift: Can occur due to faults in the coupling system, incorrect guard settings, or poor coordination.
  • Incorrect sizing: Too small a battery results in short operating time; too large a battery results in unnecessary costs.
  • Lack of load prioritization: Without clear rules, the system may become unstable or critical functions may fail.
  • Operation and maintenance: Without regular testing, the solution may fail when needed.

A simple way to reduce risk is to ensure that there are clear operating instructions: What loads are on the island operation circuit, how is switching performed, and how is it subsequently checked that everything is running stably? This is often where projects win or lose in practice.

Island operation compared to off-grid generator and hybrid

Island operation is not the same as off-grid. Off-grid is permanent self-sufficiency without connection to the public grid and typically requires larger battery storage to cope with several days without solar production. An emergency generator can provide long operating times, but requires fuel, active management, and maintenance, and it is noisy and produces emissions. Hybrid solutions often combine batteries and generators: the battery handles rapid changes and stable power, while the generator can extend operating time.

The choice between island operation, generator, and hybrid therefore largely depends on what you want to optimize: fast and automatic transition, longest possible operating time, or lowest possible complexity in everyday use. It often makes the most sense to start by defining your requirements for operating time and critical loads and then choose the solution that matches those requirements with the least possible risk and simplest operation.

FAQ about island operation

  • What is island operation? Island operation is when a building/installation is supplied locally by its own energy sources without connection to the collective electricity supply grid, typically during a power outage or planned disconnection.
  • What is the difference between planned and unplanned island operation? Planned island operation is controlled and designed in advance. Unplanned island operation is unplanned operation of a network segment without control and can cause serious security and stability problems.
  • Can a solar cell and battery system supply neighbors during a power outage? No. Off-grid operation must be limited to the specific property, and the system must not send power to the collective power grid during an outage.
  • What does island operation typically require in a solar cell battery system? Solar cells with batteries require hybrid inverters, and island operation typically requires Transfer Switching Equipment (TSE) to ensure safe disconnection from the grid.
  • How much does a solar power system with a battery typically cost? A complete system for an average household of four people typically costs around DKK 130,000. Retrofitting a smaller battery starts at around DKK 35,000.
  • What are the typical pitfalls of island operation? Unintended island operation, incorrect dimensioning, lack of load prioritization, and lack of testing and maintenance, resulting in the solution not working when needed.

Contact us

Do you have questions or need advice? Our experts are ready to help you.

Contact support

If you would like to contact support, please call +45 35 153 123 or send an email to support@xolta.com.

Contact sales