Expansion of grid connection

Expanding your grid connection becomes relevant when your existing electricity connection can no longer keep up with growing electricity consumption or increasing electricity production. This is typically seen in electrification (e.g., electric cars, heat pumps, and electric boilers), new business activities, or expansion with solar cells. At the same time, Denmark is experiencing a capacity shortage in several grid areas, which can lead to longer processing times, more rounds of clarification, and greater uncertainty about both time and finances. Here you will find an overview of what expanding your grid connection entails, how the process typically works, and what alternatives may be relevant if the desired capacity cannot be delivered.

What does expanding grid connection mean in practice?

Definition: Grid connection expansion is an extension or reinforcement of the collective electricity grid (distribution or transmission grid) so that new or expanded consumption or production facilities can be connected when there is insufficient capacity in the existing grid.

In practice, this means being able to get more power in (consumption) or out (production) via a connection point. This is particularly relevant when your load or production peaks at times when the grid is already under pressure. If the grid company or Energinet assesses that the grid cannot deliver the desired capacity, this may trigger a need for grid reinforcements, e.g., cables, transformer stations, or overhead lines at relevant voltage levels.

A concrete and useful focus in the dialogue is therefore to describe when and how the effect occurs: Are there short peaks, or is there a high, constant level? This type of information affects both the capacity assessment and, in many projects, which remedial options may come into play.

Expansion of grid connection in distribution and transmission networks

Expansion of grid connection can take place at several levels in the electricity grid. It is advantageous to clarify early on where in the chain your project actually "hits" a bottleneck, because this has implications for responsibility, process, and possible solutions:

  • Transmission grid: Operated by Energinet and typically comprises voltage levels above 100 kV. This is where large consumers and major production facilities are connected, among others.
  • Distribution network: Operated by local network companies and typically covers 60 kV down to 0.4 kV. The vast majority of businesses, housing associations, and small producers (e.g., solar cells) are connected to this network.

The level that will be decisive depends on your power requirements, location, and the capacity of the grid area. In practice, a project may start in the distribution grid but still be limited by conditions "upstream." Therefore, it is often worthwhile to clarify whether the challenge lies locally in lower voltage levels or whether it is related to a broader capacity limitation.

This is how the expansion of the grid connection proceeds step by step

A typical process begins with a request for grid connection (or expansion) to the relevant grid company or Energinet. Capacity, connection options, and any need for grid expansion are then assessed. The more precisely you can describe your needs from the outset, the fewer clarification rounds you are likely to encounter along the way.

1) Request for extension of grid connection

Content: The request should be precise about the desired effect, location, operating pattern, and any future expansions. Unclear or incomplete information may trigger clarification rounds and delays.

To make the request operational, it is typically advantageous to have a brief "requirements profile" ready internally: Which systems drive the power demand (e.g., charging, process equipment, heating), and which parts are business-critical? When you can distinguish between "must have" and "nice to have," it becomes easier to evaluate flexible solutions if full capacity cannot be delivered immediately.

Response times: Small renewable energy installations(≤10.8 kW) on the distribution grid are entitled to a response within 30 days of receipt of a complete application. Larger projects may take significantly longer.

2) Capacity assessment and analysis for grid connection expansion

The grid company or Energinet assesses whether the grid can handle the desired consumption/production without exceeding capacity. A key factor is the peak load – the highest simultaneous load – which is often decisive in determining whether grid reinforcement is required.

This means that it is rarely enough to know your annual energy consumption. In the dialogue, it will typically be just as relevant to be able to describe simultaneity: How many units can run at once, and how long does the peak last? If you already have measurement data, it can be useful to substantiate the operating pattern and reduce uncertainty in the assessment. If not, a conservative description can help avoid later changes that may trigger new assessments.

3) Connection point and cost-effective expansion of grid connection

Connection point: You will be assigned a connection point based on objective criteria. This may not necessarily be where you would prefer to be connected.

Principle: As a starting point, the network operator must designate the point that provides the lowest total costs for grid connection, unless another solution is agreed upon.

As a customer, it is useful to clarify what a designated connection point means for your internal installations and planning on the property: cable routing, space requirements, any building alterations, and access conditions. Although the connection point is determined based on objective criteria, your practical requirements for operation and secure access may influence which solutions are realistic to implement in practice.

4) Grid expansion, permits, and execution of grid connection expansion

If there is a lack of capacity, expanding grid connections may require planning, regulatory processes, and the physical establishment of new infrastructure. In some cases, environmental assessments and special permits may be required, e.g. if the route affects protected areas. Therefore, larger projects can take years – not only for administrative reasons, but because the expansion itself is extensive.

Here, it is often helpful to plan along two tracks: (1) the long-term track, where the grid expansion is implemented, and (2) the short-term track, where you assess whether operations and projects can be temporarily adapted. This may involve, for example, prioritizing which loads should be able to run without restriction and which can be managed more flexibly for a period of time.

Expansion of grid connection and regulations: Who does what?

Expansion of grid connection is regulated by both Danish and EU regulations. Key players in Denmark are:

  • Danish Energy Agency: Administers legislation on the electricity market and develops frameworks for production, transmission, and distribution.
  • The Danish Energy Regulatory Authority: Economic regulation of Energinet and network companies, including tariffs and connection conditions.
  • Energy Complaints Board: Handles complaints about decisions made by network companies and the Danish Energy Regulatory Authority.

Electricity generation plants are subject to technical requirements under RfG (Requirements for Generators), and larger plants may require compliance tests or simulations to document properties such as voltage stability and robustness in the event of grid disturbances.

For you, this means in practice that there may be both a legal and a technical "documentation task." It is advantageous to clarify early on who will provide which input (designers, installers, suppliers) and how documentation, testing, and any simulations will be included in the schedule. This reduces the risk of technical clarifications coming late and affecting commissioning.

Economics of expanding grid connections: Connection fees and when to build grids

Connection fee: The one-time payment charged for connection or expansion. The fee must be cost-based and transparent, and it is borne by the party giving rise to the expansion.

Standard connection fee: There are standard fees that are intended to ensure more uniform payments across the country. Examples from January 1, 2026:

  • Detached house/holiday home (25 A): approx. DKK 17,950 excl. VAT (DKK 22,438 incl. VAT).
  • Standard apartment: approx. 9,800–12,250 DKK.
  • Housing for the elderly/young people: approx. DKK 5,510–6,888.
  • Business (A-high): approx. DKK 600,000 per MVA excl. VAT.

The point of the examples is to distinguish between "standard connection" and situations where the project actually triggers new network infrastructure. This distinction is central to the budget and decision-making basis.

Important for your business case: Standard contributions only cover situations where no grid expansion is required. If expanding the grid connection requires a new grid (cables/stations/overhead lines), the costs can be significantly higher – in large projects, in the order of many millions of kroner.

To make the finances more manageable, it may be relevant to work with scenarios: What does it mean for your project if you reach full capacity quickly, as opposed to if the grid needs to be built? And which parts of the investment (e.g., internal electrical systems and operational adjustments) can be planned so that they still provide value even if the schedule for grid expansion changes?

Capacity shortages and waiting times for grid connection expansion

Capacity shortages are a key reason why expanding grid connections can be difficult. In some grid areas, electricity consumption is expected to increase by 39% from 2025 to 2034, while solar cell production may grow significantly during the same period. This combination increases the load on the distribution grid.

At the same time, Energinet has had many projects in the pipeline, and large consumers can put considerable pressure on capacity. When new infrastructure needs to be built, it can require lengthy approval and construction processes. Energinet has planned to build approximately 2,700 km of new power cables or overhead lines in 2024-2030 and an additional 3,000-4,000 km in 2030-2050.

In practice, capacity shortages mean that you should actively address uncertainty in both time and delivered capacity. A robust approach is to clarify whether your operations can function during a period of restrictions, or whether you have workloads where even short-term restrictions are unacceptable. This choice affects whether flexible connection agreements or local solutions may be relevant as a temporary or permanent part of the setup.

Flexible connection agreements rather than expansion of grid connection

A newer option is flexible connection agreements, also referred to as limited grid connection or interruptibility agreements. Here, the customer can obtain faster and cheaper connection in exchange for accepting restrictions on access to the grid, typically during periods of high load.

To assess whether a flex agreement is relevant, it is useful to specify the restriction: What part of consumption/production can be regulated, and what are the consequences if grid access is reduced? With this clarification, it becomes easier to determine whether the agreement can be used as a bridge to later full capacity, or whether the restriction affects business-critical functions.

  • Permanent interruptibility: The network operator may reduce or interrupt the connection in the event of bottlenecks.
  • Temporary limited connection: Restriction for a period until network expansion, after which full connection can be achieved upon payment of the full contribution.
  • Stacked/partial interruptibility: Downward regulation is distributed proportionally among customers in the event of grid restrictions.

Trade-off: The agreements may be unsuitable for critical operations where interruptions are unacceptable. They should therefore be assessed against your operational risk and business-critical loads. As a minimum, you should decide internally which processes can tolerate downsizing and which require uninterrupted delivery.

If grid connection expansion cannot be implemented: own production, batteries, and flexible consumption

If expanding grid connections is expensive, slow, or not possible in the short term, alternatives can reduce the need for grid capacity. The common denominator is that you either produce more locally, store energy, or shift the load so that the peak load is lower.

  • Self-production and storage: Solar cells combined with battery storage can reduce grid dependency. In some business cases, the combination of solar cells, batteries, and intelligent energy management can reduce peak grid load by 60–92%.
  • Flexible consumption: Shift consumption away from peak loads through planning and energy management.
  • Temporary connection via flex agreements: Accept limitations as a bridge to later full capacity.

The choice between the different tracks depends on your operating profile: Do you have consumption that can be planned, or is it locked in by production rates, opening hours, or service requirements? And do you have the space and opportunity for local production and storage? These types of clarifications are often enough to choose a realistic direction without having to decide on all the details from the outset.

At XOLTA, we work with battery solutions and intelligent control systems that can support flexibility and better utilization of local production—particularly relevant when grid capacity is a bottleneck. The focus is typically on making power demand more predictable and reducing peak loads so that your project can move forward even when grid connection expansion is uncertain.

FAQ on expanding your internet connection

  • What is grid connection expansion? It is the expansion or reinforcement of the electricity grid so that greater consumption or production can be connected when there is insufficient capacity in the existing grid.
  • Who should I contact about expanding my grid connection? The relevant grid company for connections to the distribution grid and Energinet for connections to the transmission grid.
  • How long does it take to expand grid connection? Small renewable energy plants (≤10.8 kW) on the distribution grid are entitled to a response within 30 days upon submission of a complete application. Larger projects can take years, especially if grid expansion and permits are required.
  • What determines the price of expanding the grid connection? The connection fee is a one-time payment that must be cost-based and transparent. Standard fees typically only apply when no new grid needs to be built; when expanding the grid, the costs can be much higher.
  • Can I get a faster grid connection with a flexible agreement? Yes, flexible connection agreements can provide faster and cheaper connections, but grid access may be limited or interrupted during periods of high demand.
  • What alternatives are available if expanding grid connection is difficult? Self-generation and storage (e.g., solar cells and batteries), flexible consumption, and temporary solutions via limited grid connection can reduce the need for additional grid capacity.

Contact us

Do you have questions or need advice? Our experts are ready to help you.

Contact support

If you would like to contact support, please call +45 35 153 123 or send an email to support@xolta.com.

Contact sales